Before a single brick is laid in DHA Islamabad–Rawalpindi, your house needs approved drawings, a demarcated plot and a signed inspection chart. Getting this right saves months of delay — and avoids fines, stop-work notices and problems when you apply for your completion certificate.
This guide explains DHA Islamabad building plan approval step by step: who prepares the drawings, what they must show, which documents to submit, how long each stage takes and what it costs.
Based on the DHA Islamabad–Rawalpindi Byelaws & Regulations 2022 (updated 2023). Fees and procedures are revised from time to time — confirm current requirements with the DHA Building Control Directorate before you apply.
The approval process at a glance
| Step | What happens | DHA time frame |
|---|---|---|
| 1. Site plan and possession | DHA issues the site plan and hands over possession | About 20 working days (urgent: 4) |
| 2. Drawings prepared | Architect and structural engineer prepare drawings; soil test done | Depends on your design |
| 3. Drawing submission and approval | DHA scrutinises the drawings against the byelaws | About 20 working days (residential) |
| 4. Demarcation | DHA survey team marks the plot boundaries | Within 5 days of complete documents |
| 5. Construction and stage inspections | DHA inspector checks and signs each stage | Throughout construction |
| 6. NOC for occupation | Site checked for violations before you move in | 10 days if there is no violation |
| 7. Completion certificate | Final inspection against as-built drawings | 30 days if there is no violation |
Step 1: Site plan and possession
The first step is to obtain the site plan, which shows the dimensions of your plot and the road it faces, and to take formal possession.
- 2 possession forms
- Copy of the allotment letter
- Copy of CNIC (or NICOP)
- Paid site plan and possession dues
DHA’s normal time frame is about 20 working days; an urgent site plan takes about 4 working days at extra cost.
Step 2: Get your drawings prepared by DHA-registered professionals
DHA only accepts drawings prepared by a licensed architect and structural engineer on DHA’s panel. The structural design must be done, signed and stamped by a PEC-licensed engineer.
Soil test
Before the structural design, a soil investigation is required — at least two boreholes — carried out by a DHA-approved firm or laboratory. The soil report decides the type of foundation (strip, raft or pile).
What the submission drawings must show
- Plans of the basement (if any), ground floor, first floor and roof with mumty
- Front elevation (two elevations for a corner plot) and a section through the stairs
- Elevation and section of the boundary wall, gate, ramp and road-side water channel
- External and internal dimensions, and all projections beyond the walls
- Total building height and floor levels from the reference point
- Location and size of the overhead and underground water tanks
- Separate sewerage, wastewater and drainage lines, and the reference manhole
- Thickness and cross-sections of RCC structures
- Schedules of covered and open areas, and of doors and windows
- A colour 3D (isometric) view of the house
Rules your design must follow
Most drawings are returned because the design breaks one of these limits. Your architect should check them before submission:
- Storeys and height: maximum ground + first floor, and 37 ft including mumty and water tank.
- Minimum size: DHA does not approve houses below 2,000 sq ft of covered area.
- Ground coverage: for example 70% for 250–399 sq yd plots (10 Marla) and 68% for 400–800 sq yd plots (1 Kanal), including the car porch.
- Setbacks: for example 10 ft front for 10 Marla and 15 ft front for 1 Kanal, plus rear and side setbacks.
- Mumty: maximum 11 ft high above the first-floor roof and limited in area by plot size.
- Water tanks: one overhead tank (up to 900 gallons for plots up to 1 Kanal); a rainwater harvesting tank is mandatory for 1 Kanal and above.
- Basement: only within the building line after leaving setbacks, with RCC retaining walls and waterproofing; RCC piling on all sides if deeper than 12 ft.
Step 3: Submit the drawings
Submit the following to the Building Control Directorate of your phase:
- 3 sets of submission drawings (ammonia prints) signed and stamped by the DHA-registered architect, with a soft copy
- 1 set of structural drawings on A3, signed by the DHA-registered structural engineer, with a certificate that the structure is safe
- Soil test report from a DHA-registered firm
- 3D colour view
- Copies of CNIC, allotment letter, possession form and site plan, with the NOC verified by DHA’s Transfer & Record and Finance Directorates
- The required undertakings by the owner, architect and structural engineer
- Paid scrutiny fee and refundable security charges
Fees
| Item | Amount (as per 2022 byelaws) |
|---|---|
| Drawing scrutiny – individual residential plot | Rs 20 per sq ft of covered area |
| Revised drawing – residential | Rs 50,000 |
| Completion certificate – house (first owner) | Rs 25,000 |
| Security charges | As per DHA rates; refunded when the completion certificate is issued |
For example, the scrutiny fee for a 3,000 sq ft house works out to about Rs 60,000.
Step 4: Approval
DHA checks the drawings against the byelaws. If they comply, you collect the approved drawings with a permission letter and the demarcation procedure. If there are observations, the drawings are returned to your architect with reasons, and the clock restarts once the corrected set is resubmitted.
Important: approved drawings are valid for 3 months. If construction does not start in that time, the drawings must be revalidated. Construction must then be completed within 3 years of approval, otherwise a penalty applies.
Step 5: Demarcation
After approval, DHA’s survey team marks your plot on site. Before demarcation you will need to submit an excavation plan and work method, and arrange basic material and labour for fixing the pillars. Demarcation is checked at three stages:
- Initial demarcation – pillars are fixed at the plot corners. Do not disturb them.
- After excavation of the boundary wall – checked on lean concrete (for basement houses, after the basement is complete).
- At DPC level – before any construction above plinth level.
The main building cannot start until the road-side boundary wall is built up to DPC level and checked by DHA. Water and electricity connections can only be applied for after demarcation. Note that DHA does not allow excavation during the monsoon, and demarcation stops around mid-July.
Step 6: Construction and stage inspections
- Construction must be carried out by a contractor registered with DHA.
- Keep one set of approved drawings on site at all times.
- Get every stage checked and signed on the inspection chart by the DHA inspector — you will need the original chart for your completion certificate.
- Any change to the design needs revised drawings approved before the work is done. Construction without approval can be demolished at the owner’s cost.
Step 7: NOC for occupation and completion certificate
When the house is complete, apply for an NOC for occupation before moving in. DHA inspects the house for building and property-line violations; if there are none, the NOC is issued within about 10 days.
Then apply for the completion certificate with 2 sets of as-built drawings signed by your registered architect, a soft copy, and the original signed inspection chart. If there is no violation, the certificate is issued within about 30 days. Minor deviations may be regularised by paying a penalty; major ones must be removed. The boundary wall must be complete and plastered inside and out before you apply.
Planning your budget as well? See our 2026 guide to house construction cost in DHA Islamabad, and if you live outside Pakistan, our guide for overseas Pakistanis.
Common reasons for delay
- Design exceeds coverage, height or mumty limits, or encroaches on setbacks.
- Missing soil test report or structural safety certificate.
- Drainage, sewer or water tank details missing from the drawings.
- Drawings approved but work not started within 3 months.
- Construction changed on site without revised approval.
- Inspection chart not signed at each stage.
Frequently asked questions
How long does DHA Islamabad take to approve house drawings?
For a residential house, DHA’s time frame is about 20 working days after a complete submission. If there are observations, the corrected drawings are reviewed again after resubmission.
Who can prepare drawings for DHA approval?
Only a licensed architect and structural engineer registered on DHA’s panel. The structural engineer must be PEC-licensed and sign and stamp his own design.
How long are approved drawings valid?
Three months. If construction has not started within that period, the drawings must be revalidated. The house must be completed within 3 years of approval.
What is the minimum size of house DHA will approve?
DHA does not approve house drawings with less than 2,000 sq ft of covered area.
Can I change the design during construction?
Yes, but only after revised drawings are approved by DHA. Unapproved changes can lead to fines or demolition and will hold up your completion certificate.
Let us handle the approvals for you
DHA Builders is a DHA-registered contractor based in DHA Phase 2, Islamabad. We build homes and commercial buildings across DHA Islamabad–Rawalpindi and Bahria Town. Send us your plot size and phase, and we will guide you through design, approvals and construction, with a free preliminary estimate.
WhatsApp / Call: 0321 5120210 | Email: info@dhabuilders.com | Contact form



House Construction Cost In DHA Islamabad 2026 | Grey & Turnkey Rates
[…] the full step-by-step process, read our DHA Islamabad building plan approval guide. Living abroad? See our guide to building your house in DHA from […]